On Friday June 25, Cementation hosted a barbecue to celebrate reaching a half million hours without a lost time incident. Cementation contractor, Tri-Star Industrial, catered the BBQ luncheon for Cementation employees, all shifts. On behalf of Resolution Copper, Tom Goodell expressed appreciation for the good work undertaken by Cementation.
Posts Tagged ‘headframe’
Cementation celebrates 500,000 hours
Tuesday, June 29th, 2010#10 Headframe Completed Today
Friday, March 20th, 2009
Today, Resolution Copper staff and contractors celebrated the completion of the #10 headframe at its East Plant site in Superior. The $4 million dollar project was completed ahead of schedule and with no lost-time injuries.
Highlights:
- Construction of the headframe foundation was completed by Sundt Construction using 3,100 cubic yards of concrete and 245 tons of rebar in 30,500 hours.
- Cementation, the shaft sinking team, has been involved in the project since 2006 and has worked 300,000 man-hours without lost-time incident.
- Schuff Steel, a long term Arizona based steel fabricator and erector, spent 1,700 man-hours on detail drawings, 29,000 man-hours (and 590 tons of American made steel) on fabrication and 7,500 man-hours on erection of the headframe.
- Key contractors involved include: Superior-based contractos Albo Guzman Trucking, Superior Environmental and Ubiquity, Globe-based contractors Marcanti Electric and DalMolin Excavating; Wackenhut and CH2MHill.